Employ the best contractors before Planning Shutdowns:
Everybody in business looks for the best price with contract work and services. The temptation is to go with the lowest quotation when employing shutdown or turnaround contractors. However, this may not be the best option as shutdowns are projects where time is of the essence. Employing the most experienced contractors, even if they are the most expensive, could be the difference between finishing the project on time and, ultimately, on budget.Quality Assurance and Quality Checking program
A proven method for quality assurance is a two part tagging system where all machinery is initially tagged and checked by the foreman after it has been completed and there is a further check by the QA representative at the end as a sign off for the machine to re-enter service. Having systems in place such as these help to ensure nothing is missed and even though it is time consuming it does pay off for the project as a whole. All QA and QC elements should be clearly outlined in the contractor orientation to avoid confusion.Don’t forget to Educate
The contractor orientation for shutdowns and turnarounds is perhaps one of the most important orientations in manufacturing and hard hat industries. The shortened time frame of the work and the myriad safety hazards demand well-documented procedures for contractors to follow. Shutdowns and turnarounds are intense work periods and significant gains accrue to companies who use online orientations to get through the majority of orientation materials in advance of the turnaround day. Safety training, shutdown processes, site information and contractor registration can all take place in advance of any contractors setting foot on site resulting in maximum efficiency on day one.Develop a good working relationship with your contractor
A good working relationship with contractors is a decision that is made well before any workers arrive on site. It is more a question of intention on the part of the company. Providing adequate training in advance is one element of developing a good relationship but it is not the only one. Contractor companies who are involved in the design of the shutdown plan to have a greater sense of investment in the project and a greater understanding of where difficulties might crop up. Inevitably, tasks will be shared between employees of the company and the contractor so having cultivated a joint sense of purpose between these two elements may be the difference between success and failure in the end. Finally, good communication of expected standards and consequences of failure can ease friction in the project.Provide enough time for preparation
A conservative guide for the planning of a shutdown is 4 months, though most companies do build the shutdowns and turnarounds process into their annual maintenance schedules. Assembling contractor quotations, contracts, training orientations and output downtime can not be done overnight and requires careful planning. Safety training alone for contractors who may not be familiar with the plant or site requires detailed work in preparation.